(영문) 서울행정법원 2015.05.21 2014구합69211
총회결의무효확인
Text

1. All of the plaintiffs' claims are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. Basic facts

A. The Defendant is a housing redevelopment and consolidation project partnership which obtained authorization on May 16, 2008 from the head of Mapo-gu Seoul Metropolitan Government (hereinafter “head of Mapo-gu”) for the purpose of implementing the housing redevelopment and rearrangement project (hereinafter “instant project”) on the land size of 62,245.8 square meters in Mapo-gu Seoul Metropolitan Government G G G, and the Plaintiffs are owners of land, etc. within the said rearrangement project zone.

B. The head of Mapo-gu Seoul Metropolitan Government announced a project implementation plan for the first project implementation plan for the project implementation of the project as follows: (a) the number of units of housing units classified by supply, such as the project implementation plan authorization, 39/45/52/52/52, 59/59/269/269/269/259/269/269/269/269/89/209/8269/4259/269/89/209/4259/209/4269/89/4209/4269/89/4209/4269/1269/4209/4269/4209/12616/12, 20984/16/12, 2012/17/17/201.

According to the above, the project implementation period is 60 months from the date of project implementation authorization and includes the following housing construction plan. 2) The Defendant obtained the project implementation authorization (the Mapo-gu Seoul Metropolitan Government public notice I) on March 20, 2014. According to the modified project implementation plan (hereinafter “ modified project implementation plan”), the project implementation period is 60 months from the date of project implementation authorization, and the contents of the housing construction plan are as follows:

The following differences are the project implementation authorization for the first lease of apartment units (multi-unit housing) of 52 T 52T 52T 59A 59B 84B 84C 84D 96B 112A 112B 12B 12B 182A 1122B 112B 112B 18248984 984 12256 1256 346 1253 1286 2287 22887 22222 22222222222256 346 25287 22222162(multi-unit housing) and changes in project implementation authorization:

A total floor area of 196,133.