Text
1. The defendant received KRW 2,300,100 from the plaintiff and simultaneously received KRW 31,596,620 from the plaintiff and 10,670 among them.
Reasons
1. Basic facts
A. The Plaintiff is a person who operates a construction business under the trade name of “B,” and the Defendant Company is a corporation that conducts construction work business, engineering work business, etc. as a target business.
B. On August 11, 2015, the Plaintiff entered into a construction subcontract (hereinafter “instant contract”) with the Defendant Company on the construction of reinforced concrete (hereinafter “instant construction”) among the construction of the new construction of the Dongdaemun-gu Cdong Child Care Center (hereinafter “instant construction”). However, on September 19, 2015, only the construction term was changed by October 20, 2015.
1. Project owner: The name of the D prime contract: the new construction of the Cdong-gu Child Care Center during Gyeyang-si; and
2. Title of subcontracted construction: Construction of reinforced concrete among the construction of child-care centers in Ansan-si;
3. Construction place: One parcel outside the E in Ansan-gu.
4. Period of construction: 76,670,00 won (including value-added tax) for the period of construction on August 11, 2015, and September 20, 2015, as completed;
9. The rate of warranty bond: 3%; 11. The rate of warranty bond for delay: 1/1,000 specially agreed;
2. Amount of progress payment (1) : 11,00,000 won (including value-added tax) : The amount to be paid 11,00,000 won (2) ; (4) the amount to be paid 2,00,000 won (including value-added tax) ; (5) the amount to be paid shall be 22,00,000,000 won (including value-added tax on October 17, 2015) at the time of installation of a cover board (including value-added tax) at the time of installation of a cover board within seven days after the completion of the framework project, within seven days after the completion of the framework project, including the amount to be paid 11,00,000,000 won (6) ; (6) the amount to be paid 11,670,000 won (including the amount to be paid; 1,000,0000 won); and (3) the purport of pleading as a whole 1, / evidence ;
2. Determination
A. We examine the determination of the Plaintiff’s cause of claim, and the fact that the Plaintiff, at the latest, delivered the instant construction work to the Defendant Company after completion of November 3, 2015 is the Defendant Company.
The Plaintiff completed the instant construction work on October 20, 2015, as stipulated in the instant contract.