logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울북부지방법원 2017.11.02 2015가합23349
손해배상(건)
Text

1. The Defendant’s KRW 318,50,000, and the Plaintiff’s annual interest from March 1, 2015 to November 2, 2017.

Reasons

A. Under a standard contract for construction works [1] : The ordering person: the Plaintiff (hereinafter referred to as “A”) and executor: the Defendant (hereinafter referred to as “B”) [2] Construction Period: The contract amount / February 28, 2015 / [4] the contract amount: 2.450 million won (Additional tax) [6] no advance payment. Within 490 million won for the first instance portion (excluding value-added tax 20%) / within seven days after the completion of the second floor theory of the construction / within seven days after the completion of the construction / within 1.7 billion won for the second instance portion of the construction / within seven days after the completion of the construction / within seven days after the completion of the construction 7.7 billion won (excluding value-added tax 3.0 billion won) for each additional construction / within seven days after the completion of the construction / seven days after the completion of the construction / seven days after the completion of the construction / seven days after the completion of the construction / seven days after the completion of the construction 1.77 billion days after the completion date.

1. Where it is caused by natural disasters, wars, the pollution of ports, the control of epidemics, access to security, etc.;

2. Where it is impossible to carry out construction works because the supply of important payment materials that cannot be used as a substitute for B has been delayed;

3. Where the commencement of construction has been delayed or suspended due to causes attributable to Party A;

4. Where delay is caused by any other cause not attributable to B, Article 26 (Cancellation of Contracts A) 1 A may cancel or terminate the whole or part of the relevant contract in any of the following cases:

1. A contract shall have been made even after the date of commencement agreed upon by B without any justifiable reason; and

arrow