(영문) 울산지방법원 2018.05.09 2017가단18377
공사대금 등
Text

1. The Defendant shall pay to the Plaintiff KRW 110,029,150 and the interest rate of KRW 15% per annum from April 12, 2018 to the date of full payment.

Reasons

1. The Plaintiff, as indicated in the claim, entered into a contract with the Defendant for construction of structures and for construction of paintings, issued and supplied tax invoices (excluding surtax) on eight occasions from April 30, 2017 to July 24, 2017, - KRW 847.60,00 on April 30, 2017 - KRW 68.9 million on April 30, 2017 - KRW 99 million on May 31, 2017 - KRW 8,515,500 on May 31, 2017 - KRW 136.5 million on June 30, 2017 - KRW 50,000 on June 24, 2017, including the total value of supply: KRW 17.5 million on June 25, 2017 - KRW 200,71.71.757.200.

2. Judgment by service (Article 208 (3) 3 of the Civil Procedure Act).