logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 광주고등법원(전주) 2014.09.25 2013나152
공사대금 등
Text

1. Of the judgment of the court of first instance, the part against the defendant limited liability company A and C shall be revoked, and the above revoked part shall be revoked.

Reasons

1. Basic facts

A. C Co., Ltd. and Defendant C Co., Ltd. (hereinafter “C-Japan”) are Japan companies established on March 7, 198 (a place of business in the Republic of Korea: Jeonnam-gunK), and Defendant C-Korea Co., Ltd. (hereinafter “Defendant C-Korea”) is a Korean company established on November 1, 201, and the above C-Japan and C-Korea are both Japan L, the representative director of which is Japan.

On the other hand, Defendant B is a representative in the Republic of Korea of C day.

B. The Plaintiff’s claim for construction payment 1) Defendant limited liability company A (hereinafter “Defendant A”).

(2) On October 2010, a Japanese company entered into a contract for the construction of steel framed among the new construction of the “G building” located in the east of Japan and entered into a contract with the main office of Japan (Korean business office) and the E Co., Ltd. (hereinafter “E”).

(1) On November 29, 2010, the Plaintiff entered into a subcontract with the main office of Korea (Korean place of business) for construction works to produce and supply the steel framed BH in connection with the said construction works (hereinafter “instant subcontract”) with the cost of construction work fixed from January 29, 201 to September 201 (hereinafter “instant subcontract”).

() On June 7, 2011, the Plaintiff entered into a sub-subcontract with E to adjust the contract amount of KRW 242,00,000,00 for the said construction work, from June 7, 201 to September 30, 201, and the construction cost from June 7, 2011 to September 30, 201, the Plaintiff paid the fixed amount each month and paid the final volume at KRW 310,00 per ton (hereinafter “instant sub-subcontract”).

(2) After that, the Plaintiff settled the construction price of the instant sub-subcontract with E in the final settlement of KRW 580,654,967, and the construction price of KRW 228,000 remains after receiving a partial repayment from E. The Plaintiff declared that E cannot pay the construction price any longer due to business aggravation on August 8, 2011.

C. Defendant B, in writing of the Defendants’ written statement of direct refusal, etc., shall be August 12, 201, which was after E declared insolvent.

arrow