Text
1. The Defendant’s KRW 24,342,790 for the Plaintiff and the following: 5% per annum from December 10, 2016 to February 27, 2020 for the Plaintiff.
Reasons
1. Basic facts
A. On February 2, 2015, the Plaintiff and the Defendant concluded a construction contract for the construction of the Defendant’s six factories and one office building (hereinafter “instant building”) (hereinafter “instant construction”) on the ground, including Pakistan, in which around 480 million won for the construction cost and May 2015 for the completion of the construction completion plan to the Plaintiff by setting the construction cost as KRW 48 million for the construction cost and the completion of the construction completion plan (hereinafter “instant construction contract”).
(hereinafter “instant construction contract”). Details of the construction contract are as follows.
Contract for Construction Work Contract
2. On-site address: D in cases of strike.
4. The fixed amount of KRW 192,00,000 for the remainder of the construction cost (daily gold KRW 480,000) shall be the scheduled date for the completion of the construction work within 90 days after the completion of the construction work: the fixed date for the completion of the construction work on April 5, 2015: the commencement date of the construction work on May 5, 2015: the Plaintiff’s construction work on the above parcel number shall be equivalent to the written estimate submitted to the Defendant. 3) In addition to the written estimate, the construction work on the above parcel number shall be subsequently conducted under consultation.
4 A contract shall be concluded in accordance with a written estimate.
Terms and Conditions of Special Agreement
2. Matters other than estimate separately;
4. If any additional check occurs, the additional check shall be executed after the approval of the project owner, and shall be settled after the completion.
5. The terms and conditions of the construction shall be the basis for completion and all responsibilities except the interior of a dormitory on completion shall be borne by the Plaintiff.
B. The Plaintiff completed the instant construction, and the Defendant did not pay KRW 63,741,34 to the Plaintiff.
[Ground of recognition] Facts without dispute, entry of Gap evidence 1 to 9, purport of the whole pleadings
2. According to the above facts of recognition as to the cause of the claim, the defendant is obligated to pay the remaining construction cost of KRW 63,741,334 and delay damages to the plaintiff, except in extenuating circumstances.
3. Judgment on the defendant's assertion
A. First of all, the defendant's argument that there was a defect in each part related to the plaintiff's construction project of this case, such as the attached list 1, and the plaintiff is obligated to pay damages in lieu of the defect repair of the part.
However, the damages in lieu of the defect repair as a result of the appraisal are 60,388.