Text
1. The defendant's KRW 104,838,356 to the plaintiff A, KRW 74,358,533 to the plaintiff B, and KRW 1,378,306 to the plaintiff C, D, E, and F, respectively.
Reasons
1. Circumstances and results of appraisal of the ruling;
A. The Plaintiffs’ relationship and the details of land inheritance were owned by 250/936 shares (hereinafter “G land”), 250/936 shares (hereinafter “H land”), and 1,574 square meters prior to I (hereinafter “I land”) out of 1,453 square meters prior to G when G, and 230 square meters prior to H, respectively. As the deceased died on September 20, 207, Plaintiff B, the wife of the deceased, inherited 3/13 shares of each of the above lands, and the remaining Plaintiffs, the deceased’s children, inherited 2/13 shares of each of the above lands.
(b) Business approval and public notice - Business name: Road business (construction works on Expressway): Public notice: M publicly notified by the Ministry of Land, Transport and Maritime Affairs on June 17, 2009 - Business operator: Defendant;
C. The Central Land Expropriation Commission’s ruling on expropriation on March 22, 2013 - Land subject to expropriation: G land, H land, I land, N 347 square meters (hereinafter “N land”), public cemetery 1,983 square meters (hereinafter “O land”), G, O’s trees, graves, stone embankments, etc., and obstacles, 294 square meters (hereinafter “P land”) in the P P at the time of the Plaintiff’s racing owned by the Plaintiff, and each of the above land is included in G land, H land, I land, I land, N 347 square meters (hereinafter “N land”), and G, 1,983 square meters (hereinafter “O land”), and 294 square meters in the P at the time of the Plaintiff’s racing owned by the Plaintiff (hereinafter “P land”). - Compensation for expropriation is described in the following specifications:
- Commencement date of expropriation: d May 15, 2013
The Central Land Tribunal made an objection on October 24, 2013 (hereinafter “instant adjudication”): The content of each of the instant adjudication is deemed omitted from the scope of compensation for losses, and the compensation for the entire obstacles (the detailed details are recorded in the list of obstacles; hereinafter the same shall apply) shall be increased as indicated below in the list of compensation for losses by including some of the trees on each of the instant lands in the scope of compensation for losses, and the compensation for losses for the entire obstacles (the same shall apply to the list of obstacles; hereinafter the same shall apply) shall be increased as indicated in the list of compensation for losses, while the compensation for losses for each of the instant lands shall be increased and the concrete packaging structures on each of the instant lands shall