(영문) 서울서부지방법원 2016.07.20 2015가합38262
정산금
Text

1. The Defendant’s KRW 365,961,931 as well as 6% per annum from June 1, 2014 to December 14, 2015 to the Plaintiff.

Reasons

1. Facts of recognition;

A. The Plaintiff is a company with the purpose of developing software, etc., and the Defendant is a company with the purpose of casino business, etc., which operates a “nuriwon”.

B. On August 22, 2012, the Plaintiff entered into a service contract with the Defendant for the development and operation of the Hawon mobile skiing bus system (hereinafter “instant service contract”) and its main contents are as follows.

Contents of the instant service contract - Contract Amount: 303,050,000 won (including value-added tax) - Total service share amount: 303,050,000 won (including value-added tax): Contract period: from August 27, 2012 to August 26, 2014 (2) - Construction of a system for real-time certification and real-time certification of mobile skiing bus system and generation, transmission, transport, download, storage of mobile boarding tickets (30 units), establishment and operation of a customer center's operating organization, such as establishment of a system for vicarious operation and operation of sales channels, sales management, sales management, and operation of an on-site operation and management of an on-site, operation and other matters of the system: by no later than December 13, 2012;

- Business budget: All operating costs will be determined and implemented by fee rates between bus operators and system operators after the selection of the operator of the Skib bus in the future.

- Special Conditions: To pay the actual cost of issuing mobile boarding tickets in consultation with the system operator at the time of commencement of the opon-on-house, the mobile boarding right is issued to the opon-on-house owner.

(Fees for the operation of the Si PPP on PP shall be paid to the Si PPP on PP on PP on PPs.

The Plaintiff’s development and operation of the system has completed the system development in accordance with the instant service agreement, and during the 12/13, 13/14, 14, 12/14, 12/14, 200 Pison Pison and Pison Pison.