1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Facts recognized;

A. Hyundai Construction Co., Ltd. (in the case of a corporation for convenience, the portion of “stock company” in the name of the Plaintiff et al. shall not be indicated separately), Daewoo Construction, Samsung C&T Construction, Samsung C&S Construction, SS Construction, ZS Construction, Large Forest Industry Development, Hyundai Industrial Development (hereinafter collectively referred to as “7 large construction companies”), and the Plaintiff and Ringle Construction, KcC Construction, Hanjin Heavy Industries, T&S Construction, T&S Construction, T&S Construction, T&S Construction, T&S Construction, Geumbu Construction, F&S, T&S Construction, Gyeongnam-Namnam Enterprise, T&S, T&T, T&T, Samsung Heavy Heavy Industries, and Han ( collectively referred to as “14 construction companies, including the Plaintiff and others,” and the above 7 large construction companies, including the above 7 large construction companies, are 14 construction companies under the Monopoly Regulation and Fair Trade Act and 28 companies under the Fair Trade Act (hereinafter referred to as “Plaintiff and others, etc.,”).

B. A summary of construction work for the high-speed high-speed rail 1) The construction work for the high-speed high-speed rail 1) is a construction work for the high-speed rail 184.534 km in total length which is linked to the ocean-going high-speed rail 184.534 km in length. This, along with the high-speed high-speed rail 1, includes approximately KRW 8.352.9 billion project cost for the construction work for the high-speed high-speed rail 19 construction work for the high-speed high-speed rail 2) divided into 19 construction sections.

Among them, ① Section 1-1 and Section 3-2 are the design and package deal method; ② Section 1-2, Section 1-4, Section 2-3, and Section 4-2, the alternative bid method; ③ the rest of Section 13 (hereinafter “instant Section 13”) are the separate design and construction method, and the minimum bid amount is the successful bid method.