logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원 2018.08.17 2017가합1598
공사대금
Text

1. The plaintiff's claims against the defendants are all dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On July 5, 2014, Defendant B, as a joint and several surety for Defendant B, as a contractor for Defendant C, as a joint and several surety for Defendant B, and as a contractor for Defendant D (hereinafter “D”), the Plaintiff, who is employed as an auditor, was drafted on July 5, 2014, a written contract for the construction of the three-story neighborhood living facilities in the third floor of the building on the ground of five lots (hereinafter “instant land”) (hereinafter “instant building”).

(hereinafter referred to as “instant contract”). 1. Construction name: All the works up to the reinforcement and completion of the structural frame of commercial buildings;

2. The construction site: G, E, H, I, J, and K of Incheon Strengthening Forces.

3. Scheduled date of commencement: The scheduled date of completion on July 20, 2014: Additional amount of construction cost on October 30, 3014: 2 billion won (excluding value-added tax): Special conditions for the construction contract, referring to the special conditions for the construction contract.

3. After the commencement of construction works, Defendant B shall enter into an agreement on provisional registration with a person designated by D.

- At the same time, Defendant B made a full payment of the construction cost and D made a provisional registration at the termination date.

5. An agreement that the construction cost shall be fully paid simultaneously with a loan for completion.

Additional - Financial costs: The financial costs (interest on 2 billion won) of the Yangyang Agricultural Cooperatives (hereinafter referred to as the "Yyang Agricultural Cooperatives") during the construction period are agreed to be paid by D on a large basis.

(Settlement of Actual Expenses) 8th day of each month, 12 million won - Civil engineering expenses (Settlement of Actual Expenses): 200 million won shall be paid in all amounts of floor works other than the area of the building.

- Design cost: Amount equivalent to the contract - The cost of structural safety diagnosis: 13 million won - the cost of electricity, water supply and sewerage, and usage fee during the construction period - all the cost incurred from other works - the cost of KRW 100 million due to the need for other works - the cost of borrowing to Defendant B at an appropriate time.

(2-3 times) In addition to the construction cost (cash) the three-story R-27, and 28 (Design Drawings Standards) are agreed to be transferred to D (the person designated by D) as transfer cycle.

- Time of transfer: after completion.

arrow