(영문) 인천지방법원 2020.08.28 2019가합51856
공사대금
Text

Defendants jointly and severally liable to the Plaintiff KRW 216,824,160, and Defendant B with respect thereto from January 16, 2019; and Defendant C with respect to the same.

Reasons

1. Facts of recognition;

A. A. Around March 2017, the Plaintiff entered into a contract with the Defendants for a new construction project of KRW 1,360,000,000, which is contracted from the Defendants for KRW 1,360,000, in Seoul Central-gu D, E Urban Residential Housing (hereinafter “D Housing”) and E Housing (hereinafter “E Housing”).

(hereinafter referred to as “the primary contract”). (b)

On April 2017, the Plaintiff: (a) divided the first contract entered into between the Defendants and the Defendants for each of the instant housing into a single contract with each of the instant housing units; (b) entered into a contract for the new construction of D Housing with each of the instant housing units in KRW 665,60,00,000; and (c) entered into a contract for the alteration of the E-Newly

(hereinafter referred to as “each of the instant changes”). C.

On September 8, 2017, the Plaintiff concluded a contract with the Defendants to change the construction cost, construction period, payment terms, and cost-sharing subject of each of the instant modified contracts.

The "final contract of this case" is "each final contract of this case" and "the contract of this case" is "the contract of this case" as a whole.

1) The amendment to each of the above agreements is as follows. The construction period of KRW 665,60,00 (excluding value-added tax): 890,420,695 (including value-added tax): The completion on April 20, 2017: the commencement on April 20, 2017: the completion on April 20, 2017: the extension on December 15, 2017; the first period of 1. The first period of 00,000,000 won: 30,000,000 won: the first period of 6.0,000,000 won; 265,60,000,000 won; the second period of 7.1: The amendment to the construction period of 20,700,700,000 won and the second period of 1.65,000,000 won and the second period of 2.75,07: The Defendants included the agreement with the Plaintiff and the relevant construction period of 2.