(영문) 서울동부지방법원 2018.03.28 2017나1235
공사대금
Text

1. The plaintiff (Counterclaim defendant)'s appeal is dismissed.

2. The costs of appeal shall be borne by the Plaintiff (Counterclaim Defendant).

purport, purport, and.

Reasons

1. The court of first instance dismissed both the Plaintiff’s claim on the principal lawsuit and the Defendant’s counterclaim, and only the Plaintiff appealed on the principal lawsuit, the scope of the judgment of this court is limited to the part of the claim on the principal lawsuit among the judgment of the court of first instance.

2. The reasons for the admitting the part of the claim in the judgment of the court of first instance are that "the construction work mentioned in the table 1 and the table 2 shall be added to "the construction work mentioned in the table 1 and the table 2 for the same reason as the plaintiff asserts" and "the contents mentioned in the table 1 and the table 2 shall be added to "the construction work mentioned in the above table 1 and the table 2" of the court of first instance from the 5th judgment to the 5th judgment, "the construction work mentioned in the above table 1 and the table 2 shall be added to "the construction work mentioned in the above table 1 and the table 2" of the second through the 6th judgment from the 7th judgment to the 4th judgment without any reason."

3. The plaintiff asserts that the additional part of the plaintiff asserts that the additional construction works of the plaintiff's assertion were illegal according to the result of the construction cost appraisal entrustment by the Korea Disaster Institute, a foundation of the court of first instance, and that the rejection of the above appraisal entrustment without reasonable grounds.

Therefore, the defendant is a stock company in full view of the following: (a) 15, 16, 18 evidence 1 to 3; (b) 17 evidence 17; (c) 1 to 7; (d) 20 evidence 20-1 to 4; (e) the result of the court of first instance’s commission of appraisal to I by the appraiser of the court of first instance; and (e) the fact-finding results and the whole purport of arguments with respect to the Korea Disaster Research Institute, a foundation of the