logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원 2018.08.07 2017가단531655
설계대금청구
Text

1. The Defendant shall pay to the Plaintiff KRW 58,30,000 and the interest rate of KRW 15% per annum from September 12, 2017 to the day of complete payment.

Reasons

1. Basic facts

A. The Plaintiff Global E&C Co., Ltd. (hereinafter “Plaintiff”) is a corporation for the purpose of architectural design, supervision, etc., and Defendant E-Bas Construction Co., Ltd is a corporation for the purpose of construction business.

B. On July 7, 2016, the Plaintiff Company and the Defendant Company are “the instant construction work” of the New Pest Korea New Pest Korea factory.

In relation to the design and supervision service contract (hereinafter referred to as "the contract of this case") with the following contents:

- The contract term of 833-4 (in the general industrial complex of Cheongcheon-do) located in the site for new construction of new PPS Korea: 0.0% of the contract amount: 0.0% of the total amount of 0.0% of the contract amount - 0.0% of the total amount of 0.0% of the cost of construction work (in the case of 0.00,000,000), - 0.0% of the total amount of 0.0% of the cost of construction work (in the case of 0.0,000,000), - 0.0% of the cost of construction work (in the case of 15,00,000,000) and 5.0.0% of the cost of construction work (in the case of 0.0% of the cost of construction work, 0.0% of the cost of construction work, 0% of the cost of construction work, installation of construction order and construction work plan, etc.

C. On July 7, 2016, Plaintiff Company made the Defendant Company and the insured as the Defendant, and made the purchase amount of insurance KRW 7,150,000.

arrow