logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2017.09.06 2017나13846
손해배상(기)
Text

1. The plaintiff's appeal is dismissed.

2. The costs of appeal shall be borne by the Plaintiff.

The purport of the claim and appeal is the purport of the appeal.

Reasons

1. Article 1 of the facts of the basis;

5. Design service period: From the contract date to the issuance of the inspection completion certificate.

6. Contract amount: Article 2 (Scope of Services) of the Hacheoncheon-gu, Mancheon-do, Mancheon-do, (259,065,00 Won) (VAT).

1.(a)

Preparation of Basic and Executing Design Documents and Seal of Completion Books

6. The defendant's work performance period shall be from the date of this contract to the date of issuance of the certificate of usage inspection.

The delivery period of the execution design documents: To supply the drawings to obtain the approval of the plaintiff so as not to hinder the commencement of construction works.

(within two months after completion of the project implementation authorization). 7. The plaintiff may request the defendant to change the contents prescribed in the preceding six paragraphs according to the plaintiff's circumstances, and the defendant shall comply with such request.

Article 4 (Contents and Payment of Design Cost)

1. The total amount of the design expenses shall be Leecheon-gu, Mancheon-gu, Mancheon-do, (259,065,00 won);

(VAT Map)

3. The design cost shall be paid as classified into:

7,719,500 won (30%) after filing an application for authorization to implement the project: Two times after filing an application for authorization to implement the project: 77,719,50 won (30%): Three times after the authorization to implement the project is granted: 77,719,50 won (30%) after the delivery of books for construction works: 4 times after the authorization to approve the use of KRW 25,906,50 (10%) (the termination of the contract) and the Plaintiff and the Defendant agree to terminate the contract, or when any of the following causes occurs:

In such cases, when the plaintiff approves the defendant's progress and recognizes it as a result, he/she may settle and pay the remuneration equivalent to the performance to the defendant.

3. Where the defendant is deemed unable to perform services any longer due to other reasons.

7. When, due to a cause attributable to the defendant, it is deemed evident that the work is not performed by the time limit specified in this contract or that there is no possibility to complete the contract; 10. If the plaintiff or defendant desires to terminate the contract, he shall notify the other party of the intention not later than

Article 15 (Indemnification)

1. When this contract is terminated due to a cause attributable to the plaintiff, the plaintiff shall be the defendant.

arrow