Text
1. The Defendant’s KRW 215,000,000 and its weight shall be the Plaintiff:
(a) From October 18, 2012 for KRW 500,000:
(b) 16,500.
Reasons
1. Basic facts
A. The plaintiff is a corporation that conducts real estate development and real estate consulting business related to construction works, and the defendant is a corporation that conducts housing construction business and partnership business agency business.
B. On October 2, 2012, the Plaintiff entered into a contract with the Defendant for performance of duties and advisory services (hereinafter “instant service contract”) with respect to the construction project of multi-family housing in the Seoul Special Metropolitan City District Housing Association (hereinafter “instant new construction project”) with the Defendant on the part of Ulsan-si, Ulsan-si (hereinafter “instant new construction project”). The main contents of the contract are as follows.
Article 6 (Selection of Construction Works) (1) In selecting a construction project for the smooth implementation of a project, the Plaintiff may first enter into an agreement on construction works with a stock company B (hereinafter referred to as “B”) and a regional housing association agent for a contract in order to select a construction project for the smooth implementation of the project.
At this time, B shall endeavor to confirm and present the minimum contract construction cost, expansion construction cost, etc. to the plaintiff, and the defendant shall satisfy the matters required prior to the conclusion of the contract construction agreement in B (data for passing through the chief Justice, land-related matters, composition of association members, etc.).
Article 10 (Service Costs) (1) The service costs for a service contract shall be KRW 400 million (excluding value-added tax).
(2) The timing and method of payment of service fees shall be as follows:
(3) The service cost shall be paid in cash within 15 days from the date on which the condition of the payment is established, when applying for the authorization of the establishment of the 2-stage intermediate payment contract in the first stage payment contract in the amount of KRW 5 million.5 million upon the application for the authorization of the establishment of the 95 million-time intermediate payment after the authorization of the establishment of the 90 million-in establishment.
Article 12 (Cancellation of Contracts)