Text
1. The Defendant’s KRW 300,000,000 as well as the Plaintiff’s annual rate of 20% from May 27, 2015 to September 30, 2015, and the following.
Reasons
1. Determination as to the cause of claim
A. If the purport of the entire pleadings is added to the evidence No. 1 and evidence No. 2-1 through No. 6, it is recognized that the Plaintiff loaned to the Defendant, as of September 19, 2014, KRW 100,000,000 to the Defendant before September 21, 2012, and KRW 99,000 to the Defendant on September 21, 2012, and KRW 20,100,000 to the due date on March 31, 2014; and KRW 31,00,000 to the due date on March 30, 2015; and KRW 10,000,00 on April 3, 2014 to the respective loans, respectively.
B. According to the above facts, barring any special circumstance, the Defendant is obligated to pay to the Plaintiff a total of KRW 300 million (i.e., KRW 100 million KRW 99 million) and damages for delay at the rate of 15% per annum under the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings (amended by Presidential Decree No. 2653, Sept. 25, 2015) from May 27, 2015 to September 30, 2015, which is the day following the day when the copy of the complaint of this case was served, as sought by the Plaintiff, to the Plaintiff, as the day when the copy of the complaint of this case was served.
2. Judgment on the defendant's defense
A. On July 21, 2015, the Defendant asserted that the original Defendant agreed to pay KRW 100 million out of the above loan amount by July 30, 2015 when the C tourist resort development project in Chuncheon, implemented by the Defendant, was finalized until July 30, 2015, and that the above loan amount shall be repaid in installments from August 30, 2015 to KRW 15 million each month as soon as the said project is delayed.
B. However, there is no evidence to prove that the original defendant agreed on the above contents, and the above defense cannot be accepted.
3. The plaintiff's claim for conclusion is accepted on the ground of the reasons.