(영문) 의정부지방법원 2016.04.19 2015구합7154
보상금증액 청구의 소
Text

1. The Defendant’s KRW 14,066,250 for the Plaintiff and 5% per annum from October 15, 2014 to April 19, 2016.

Reasons

1. Details of ruling;

(a) Business authorization and public notice - Business name: Guri-Yan Expressway construction works (three-dimensionals at Guri-si): Public notice: June 5, 2012, No. 2012-284 announced by the Ministry of Land, Transport and Maritime Affairs on June 5, 2012 -

B. The Central Land Tribunal’s ruling of expropriation on August 21, 2014 - Subject to expropriation: The compensation for each land of this case on the basis of the arithmetic average of the appraisal results of the appraisal appraisal appraisal corporation and the appraisal appraisal corporation of the date of the resolution of the resolution of the resolution of the resolution of the resolution of the resolution of the resolution of the resolution of the resolution of the resolution of the resolution of compensation for damages and the appraisal corporation of the resolution of the resolution of the resolution of the resolution of the resolution of the resolution of compensation for damages: The compensation for each land of this case on the basis of the arithmetic average of 1,185,369,750 won as shown below, 70-9 square meters for miscellaneous land of the same 770-9 square meters for miscellaneous land (road) and 1385 square meters for miscellaneous land of the same 770-25 square meters for miscellaneous land (hereinafter “each land of this case”), the date of expropriation shall be calculated as 122,924,500 won for the obstacles of this case:

The Central Land Tribunal's ruling on December 18, 2014 - Compensation for losses: Based on the arithmetic mean of the respective appraisal results of the appraisal results of the appraisal company or the appraisal company or the KCA and the KCA and the KCA and the KCA and the KCA and the KCA and the KCA and the KCA and the KCA shall increase compensation for the obstacles in KRW 129,

D. Court Appraisal - The results of commission of appraisal of each of the instant lands to appraiser A of this Court are as follows:

The court's appraisal of the land category (275,650 won) 6,891,250 won (275,650 won) on miscellaneous land and miscellaneous land and 25,891,250 won (275,650 won), 6,962,50 won (278,50 won), 770-15, 770-9, 700 won (778,900 won) on the current status of public records of miscellaneous land (830,850 won) on the land of Guri-si, Guri-si, 1385,078, 776, 50 won (78,900 won), 101,232,000 won (8,600 won) on the land of Guri-si, Dori-si, 778, 776, 500 won (78,900 won) on the land of Guri-si-si-si.

2. Determination

A. The plaintiff.