(영문) 서울중앙지방법원 2016.06.29 2014가합578348
하자보수보증금 등
Text

1. The Plaintiff:

A. Samsung C&T Co., Ltd., the litigation taking over of Defendant Samsung C&T Co., Ltd., is 912,218,566 won and 91.

Reasons

(a) Each description, the result of appraisal by an appraiser, the result of each request for supplementation or supplementation by an appraiser by this court, and the purport of whole pleadings;

2. Determination as to the existence of defects and the cost of repair

A. (A) Unlike the Plaintiff’s assertion on the project approval drawings, the items indicated below, which are non-construction or modified construction based on the project approval drawings, constitute an item of construction different from the project approval drawings without legitimate approval drawings, and thus, constitutes a defect when based on the project approval drawings.

Items 1 [Attachment 247] 1 [Public 247] 23,079,4612 [public 248] Modification of the Open Base Standards (Design:300*300/construction:200/50) 50,028,1473 [public 249] Modification of the Standards for the Open Base Standards for the Underground Parking Lot Floors (Design:300*300/construction:2050) 50,028,1473 [public 249] Alteration of the Standards for the Construction of Machinery Units (Design: 100*100/ construction: 200/2050) 7,84,7074 [public 250] Alteration of the Standards for the Construction of the Construction of the F&M Floors and Construction of the F&Ms to the extent that the Plaintiff asserted to have, or claimed to, the Plaintiff's specific extent of the Construction Claim 300/25025/29/25 of the Construction Bonds

② Defendant Samsung C&T is merely a simple apartment construction project that is not a project undertaker subject to approval of the housing construction project plan or housing site development project plan under Article 16 of the Housing Act, and is thus concluded with the redevelopment association.