(영문) 대전지방법원 2014.12.11 2013나103788
구상금
Text

1. Of the judgment of the court of first instance, the part against the Defendants exceeding the money ordered to be paid under the following subparagraphs shall be revoked.

Reasons

1. The reasoning for the court’s explanation concerning this case is as follows. The court shall dismiss, add, or delete part of the judgment of the court of first instance as follows. The defendants shall add to the judgment of the court of first instance as stated in Articles 1 and 2 of the reasoning of the judgment of the court of first instance, and shall accept it as it is in accordance with the main sentence of Article 420 of the Civil Procedure Act, except for the addition of the judgment of the court of first instance

【No. 11 and No. 4” are added to “No. 11, and No. 16.”

1) Defendant A Co., Ltd. (hereinafter referred to as “Defendant”) Company:

on February 23, 2010, the Intervenor joining the Plaintiff (Jurisdiction: Daejeon Regional Procurement Service; hereinafter referred to as the “Korea”).

(E) As between the Defendant Company and the Plaintiff’s Intervenor E University (hereinafter “E”).

F. F. F. F. F. F. (hereinafter “instant construction”)

(1) A contract was entered into between the Plaintiff and the Plaintiff to carry out a performance guarantee insurance contract (hereinafter “the performance guarantee insurance contract”) with the terms of KRW 1,082,794,00 for the construction cost, KRW 216,558,80 for the contract deposit, and the performance guarantee insurance contract with the Plaintiff, instead of the contract deposit, is called the performance

The insured was issued upon entering into the contract and submitted a guarantee to the Republic of Korea. The insured amount of the insurance coverage amount of the Daejeon District Government of the Republic of Korea: the insurance coverage amount of KRW 216,58,800: from February 22, 2010 to August 24, 2010 (Provided, That the insurance coverage period is extended from February 22, 2010 to March 31, 201). Under the instant performance guarantee insurance contract, when the Defendant Company paid the insurance amount due to the occurrence of an insured event due to failure to perform its obligation under the instant construction contract, the Defendant Company shall not exceed the maximum overdue interest rate out of the insurance amount paid to the Plaintiff and the general interest rate in arrears in a commercial bank.