All of the plaintiffs' claims are dismissed.
All the costs of lawsuit shall include the part resulting from the supplementary participation.
Reasons
Details of the disposition
On October 15, 2019, pursuant to Article 6 of the Special Act on Public Housing, the Defendant designated the E-dong, Fdong, Gdong, Hdong, I Dong, Jdong, Jdong, Kdong, and L-dong 6,491,155 square meters as a C public housing district (hereinafter “instant public housing district”), and designated the Intervenor joining the Defendant (hereinafter “the Intervenor”) as a public housing project operator that created the instant public housing district.
(Public NoticeD of the Ministry of Land, Infrastructure and Transport; hereinafter "Disposition in this case"). In order to make the disposition in this case, it shall undergo deliberation by the Central Urban Planning Committee under Article 106 of the National Land Planning and Utilization Act, and the main contents of the agenda for deliberation are as follows:
The outlined location: Hanam-si, Fdong, Gdong, Hdong, Hadong, Jdong, Hadong, Kdong, and Ldong area: 6,491,155 square meters (around 1,964 square meters): The period for the project of the intervenor: Population and housing plan - From 2019 to 2028 - Housing construction - 80,000 population: 32,000 housing construction - Development density: 123 man/ha population and housing construction plan (draft) are located within the public housing zone of this case.
Plaintiff
A Co., Ltd. (hereinafter referred to as “Plaintiff A”) owns each land listed in paragraph (1) of the attached Table, and Plaintiff B owns each land listed in paragraph (2) of the attached Table.
[Reasons for Recognition] Facts without dispute, Gap evidence 2, 3, Eul evidence 6, Eul evidence 4, Eul evidence 4, Eul evidence 1-A, Eul's assertion of the purport of the whole pleadings, and Eul's assertion of the purport of the whole argument.
Two bonds buildings were newly constructed on each land listed in the port.
In the case of each building above, the expenses required in the new construction process not only exceed 10 billion won, but also the remaining period remains considerably.
In addition, the plaintiff B appears to mean the cafeteria and the building on the P ground in the name of "M" in the land listed in the attached Table 2 (g) of the attached Table 2, and the owner on the register is Q.
The details of buildings on the registry of the relevant building shall be as follows.