(영문) 대전지방법원 2019.06.13 2018가합100025
부당이득금반환 등
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Facts of recognition;

A. The Defendant is a housing reconstruction and improvement project association under the Act on the Maintenance and Improvement of Urban Areas and Dwelling Conditions for Residents, which is promoting a housing reconstruction project (B apartment reconstruction and rearrangement project; hereinafter “instant reconstruction project”) with the housing reconstruction project district of the Dong-gu Daejeon District of 108,347 square meters as the project implementation district.

B. On July 2004, the promotion committee for the establishment of the instant reconstruction project concluded a contract for the specialized management of the instant reconstruction project (hereinafter “instant contract”) with the Plaintiff, a company operating the rearrangement project management business, by setting the contract unit price of KRW 19,000 per square meter (a separate value-added tax and total contract amount shall be settled as the area finalized after the authorization for the implementation of the project), and from the date of conclusion of the contract for the business service period to the date of completion of occupancy (the date of liquidation of partnership).

The content related to the instant lawsuit in the instant service contract is as follows.

Article 3 (Scope of Services) The plaintiff shall, with the defendant's approval, seek advice and support for the performance of the following affairs related to the reconstruction project of this case, and the preparation and processing of documents related to the services shall be governed by the provisions of the Act on the Maintenance and Improvement of Urban Areas and Dwelling Conditions for Residents, the Daejeon Metropolitan City Ordinance, the Ordinance of Daejeon Metropolitan City Ordinance, the

1. Consultation on affairs related to authorization and permission and management of partners 1) Affairs related to safety diagnosis 3) Affairs related to safety diagnosis 4) Affairs necessary for authorization for establishment (4) affairs related to operation of an association, various meetings, appropriate project plans, etc. 4) affairs necessary for authorization for establishment of an association. ① Preparation of documents related to authorization for establishment of an association, preparation of articles of association, preparation of articles of association, and preparation of a list of union members, representatives, and executive officers, etc. (2) Preparation of all kinds of written consents. (4) Preparation of documentary evidence of ownership of union members (a confirmation of land use plan, land cadastre, land register