Text
1. The Defendant’s transfer of land to the Plaintiff at Daegu High Court Decision 2011Na6176 decided July 26, 2012.
Reasons
1. Basic facts
A. On the ground of the real estate listed in [Attachment List Nos. 1 to 6 (hereinafter referred to as the “instant building”) a new real estate (hereinafter referred to as the “instant building”) as listed in [Attachment List Nos. 7] was newly constructed by the PeneN Co., Ltd., Ltd. on or around October 2006, purchased the instant building from the PeneNanland and acquired its ownership. On June 9, 2008, the Defendant acquired the ownership by fully paying the price for the instant building on or around June 24, 2008 at the voluntary auction procedure for the instant building site.
나. 피고는 2008. 7. 4. 휴엔휴를 상대로 대구지방법원 2008가합7271호로 이 사건 건물의 철거 및 부당이득금의 반환을 구하는 소를 제기하였고, 위 법원은 2009. 9. 30. '휴엔휴는 원고(주식회사 엠피투자개발, 이하 '엠피투자개발'이라 하고 ‘기초사실’ 란에서 이 사건 피고의 표시는 위 회사명으로 대신한다)에게 이 사건 건물과 별지 도면 표시 A, B, C, D, E, F, G, H, I의 각 점을 차례로 연결한 ㈏부분 담장(이하 ‘이 사건 담장’이라 한다)을 철거하고 이 사건 대지를 인도하며, 엠피투자개발이 소유권을 취득한 2008. 6. 24.부터 이 사건 대지의 인도의무를 완료할 때까지 이 사건 대지의 점유사용으로 인한 부당이득금 반환으로 월 4,058,000원의 비율로 계산한 돈을 지급하라'는 전부 승소판결을 선고하였다.
C. Around February 18, 2011, the Court dismissed the part of the claim for delivery of 395 square meters of the instant land and the removal of the above ground buildings on the ground that the 395 square meters of the instant land was acquired with respect to the 395 square meters of the instant land among the instant land on the grounds that the YND had been dissatisfied with it and appealed as 2009Na8483, Daegu High Court. The said court dismissed the part of the claim for removal of the instant land and the said part of the claim for removal of the building on the ground that the 3,548 square meters of the instant land was handed over among the instant land, and removed the building on the ground from June 24, 2008 to the completion