logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2018.10.02 2017가단5244552
공사대금
Text

1. The Defendant’s KRW 17,490,00 and the Plaintiff’s annual rate of KRW 6% from June 1, 2017 to October 2, 2018, and the following.

Reasons

1. Under the underlying facts, the following facts do not conflict between the parties, or may be acknowledged by comprehensively taking account of the overall purport of the pleadings in the descriptions of Gap evidence Nos. 1-5 and Eul evidence Nos. 1-3.

C Co., Ltd. (hereinafter referred to as “C”) was a corporation that carried out a new apartment construction and sales business (hereinafter referred to as “instant business”) on the D site in March 2016, which entered into a trust contract with the Defendant around that time.

B. In relation to the instant project, the Defendant selected E Co., Ltd. (hereinafter “E”) as a contractor in relation to the instant project. around 2016, E completed the construction work for site creation even on the “land for which permission was granted for development activities for the purpose of site creation” (hereinafter “land for permission”) with respect to the “land for permission” (hereinafter “land for permission”) among the separate pages of the attached Form on the 10,074 square meters of F forest land in Sejong-si, an apartment site neighboring the apartment site construction site.

However, around May 2016, the law was collapsed.

C. Accordingly, around October 2016, the Defendant prepared a permit document (in writing by G of a stock company) to find out the legal surface of 2,506 square meters located in the upper part of the 2,506 square meters of the 2,06 square meters of the 3rd place of the 2016 forest land (hereinafter “the 2nd place of the 201st place of the 3nd place of the 3rd place of the 3rd place of the 2016th place of the 3rd place of the 3rd place of the 2016th place of the 3rd place of the 3rd place of the 2016th place of the 2nd place of the 3rd place of the

On January 23, 2017, the Defendant entered into a contract with the Plaintiff on the contract amount of KRW 400,000,000 (excluding value-added tax) for the construction for site creation (hereinafter “instant construction”) and the construction period from January 1, 2017 to May 31, 2017.

(hereinafter “instant construction contract”). The Plaintiff completed the instant construction work around April 26, 2017.

E. Meanwhile, the Plaintiff is ahead of the location where it is scheduled to be used as an access road to the above apartment site from the Defendant.

arrow