logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원 2018.05.10 2017가단26955
공사대금
Text

1. The Defendant amounting to KRW 37.4 million to the Plaintiff and the Plaintiff’s annual rate from July 1, 2016 to August 1, 2017.

Reasons

1. In full view of each statement in Gap's evidence Nos. 1 through 6 (including each number), the plaintiff engaged in heat construction and construction work is awarded a contract from the defendant who is engaged in civil engineering and construction work on June 10, 2016 to "Cheongju-do Factory," with a cost of 37.4 million won (including value added tax) and completed the above construction work on June 30, 2016 (the defendant acknowledged the conclusion of the contract with the plaintiff, but argued that the construction cost is KRW 27.5 million. However, according to the contents of text messages exchanged between the representative of the plaintiff and the defendant and the defendant's side, it is sufficiently recognized that the construction cost is KRW 37.4 million per annum from the day following the date of recording the two sides. According to the above recognition facts, the defendant is obligated to pay the construction cost of KRW 37.4 million per annum to the day of completion of the construction work and damages for delay from the date of completion of the construction work to the day of completion of 16.7.16.7% per annum.

2. It is so decided as per Disposition by the assent of all participating Justices, on the ground that the plaintiff's claim is reasonable.

arrow