logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울고등법원 2018.10.10 2018나2002354
공사대금
Text

1. Of the judgment of the court of first instance, the part against the defendant exceeding the following amount ordered to be paid shall be revoked.

Reasons

1. Basic facts

A. On October 13, 2011, the Plaintiff received a new construction of the instant multi-household housing (hereinafter “multi-household housing”) from the Defendant, Songpa-gu Seoul Metropolitan Government (hereinafter “instant multi-household housing”) from the Defendant.

(hereinafter “the instant construction contract”). The main contents of the instant construction contract are as follows.

The date of commencement: The construction cost on March 15, 201: 396,00,000 won for the expansion of the construction cost: 46,80,000 won for 46,800,000 won for 46,800,000 won for 46,000 won for 4,000 won for 4,000 won for 4,000 won for 4,00,000 won for each contract document to be attached under an agreement between the defendant and the plaintiff, and to ensure that they perform their contractual obligations in good faith, as evidence of this contract, and shall be prepared in two copies for each of them.

Documents to be attached:

1. Article 7 (Assignment of On-the-spot Agent) of the General Conditions of Contract for Private Construction Works under the General Conditions of Contract for Private Construction Works (Article 7) (1) Before the commencement of the construction work, the Plaintiff shall assign a construction engineer corresponding to the principal type of construction of the relevant construction to the site prior to the commencement of the construction work, and shall notify the Defendant

(2) Except as otherwise expressly provided for in Acts and subordinate statutes or with the consent of the defendant, an on-site agent under paragraph (1) shall stay at a site and act for the plaintiff with respect to all matters concerning execution, and shall take charge of the execution management

Article 16 (Extension of Construction Period) (1) Where the execution of construction is delayed due to reasons not attributable to the plaintiff, such as natural disasters, force majeure events, imbalance in the supply and demand of raw materials, etc., for which the defendant is responsible, the plaintiff may request the defendant to extend the construction period in writing.

(2) Where there is a request to extend the contract period under paragraph (1), the defendant shall promptly investigate and confirm such fact and extend the contract period so that the Corporation may appropriately perform it.

arrow