(영문) 울산지방법원 2014.02.12 2012가합7799
공사대금
Text

1. The Defendant’s KRW 25,844,00 for the Plaintiff and KRW 5% per annum from October 30, 2010 to February 12, 2014.

Reasons

1. Change of the original contract date on December 7, 2006, the ground for the change of the contract amount as of the date of classification of basic facts: (a) the amount to be changed on December 8, 2006, 783, 262,640 on December 23, 2009; (b) the increase or decrease in the contract amount due to price fluctuation in 19,94,017,640 on May 7, 2008; (c) the additional increase or decrease due to the increase in the quantity due to the change in site conditions; (d) the amount to be changed on May 28, 2008; (e) the number to be changed on the 19,702,525,0000,0000, or the additional increase or decrease in the construction period due to the price fluctuation in the site conditions; and (e) the additional increase or decrease in the construction period on the 206th, 2009, or the additional increase or decrease in construction period;

A. The Plaintiff entered into a contract and an amendment agreement with the Defendant for the State-funded local highway 69 lines located in Ulsan Metropolitan City (hereinafter “instant construction”). As indicated in the table below, the Plaintiff entered into a contract with the Defendant for the construction of mountain construction (hereinafter “each of the instant contracts”).

B. At the time of the instant original contract, the General Conditions of the Contract for Construction was confirmed to be part of the contract, and incorporated the General Conditions of the Contract for Construction into the content of the contract.

C. On October 29, 2010, the Plaintiff and White Construction received the construction cost as follows, and on March 15, 2007, advance payment of KRW 1,40,000,000 on March 15, 2007, which was made on July 20, 2007, the progress payment of KRW 489,020,000 on July 20, 2007, and the progress payment of KRW 710,000 on December 26, 2007, on May 30, 2008, the progress payment of KRW 907,040,000 on May 30, 200, KRW 436,670,000 on September 46, 200, 200 on June 18, 2008: