logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울고등법원(춘천) 2020.01.20 2019나50029
공사대금
Text

1. Of the judgment of the court of first instance, the defendant Gap corporation 40,007,763 won and the plaintiff Eul corporation 13,983.

Reasons

1. Basic facts

A. On May 11, 2010, Plaintiff A Co., Ltd. (hereinafter “Plaintiff A”) and Nonparty C Co., Ltd. constituted a joint supply and demand organization (representative: Plaintiff A) and entered into a contract with the Defendant for D Construction (hereinafter “instant Construction”) on the following terms (hereinafter “instant contract”).

On August 2, 2013, when the instant construction was underway, C Co., Ltd. renounced the construction work and Plaintiff B Co., Ltd. (hereinafter “Plaintiff B”) became a joint beneficiary.

[Written Contract for Construction Works] The rate of penalty for delay in total amount of KRW 8,66,80,000 for delay in total amount of KRW 8,61,77,860 for delay in construction: May 14, 2010 for the date of the commencement of 0.1% of the contract amount; and October 10, 2010 for the completion date (Provided, That the total completion date: May 13, 2013; 1,096) the documents to be attached: A detailed statement, a detailed statement, a general condition, an opinion of integrity, an agency’s official information, and an electronic contract warranty.

B. The instant contract consists of a general contract and a multiple contracts, and multiple changes have been entered into as indicated below.

(1) On May 1, 2013, May 13, 2010: 8, 67, 767, 860 or 860 on December 8, 2010: " 11,138,160,160 or 00 on August 30, 201; 20. 0. " 9,18,160,000 on December 7, 201; 20. 1. 1. 1. 1. 3. 1. 1. 1. 3. 1. 1. 3. 1. 8, 187, 810, 00 on the first 2. 1. 1. 2. 1. 2. 1. 2. 1. 1. 5. 2. 2. 2. 3. 1. 20,00 on the date of the change at the site; 3. 1. 0. 1. 3. . 2. 3. 3. 0. 2. 1. 3. 2. 2. 1. 3. 2. 1. 2. 3. 1. 1. 8

arrow