Text
1. The Defendant shall pay to the Plaintiff KRW 102,682,301 as well as KRW 15% per annum from April 5, 2017 to the date of full payment.
Reasons
According to Gap evidence Nos. 1, 2, and 3, there is no dispute between the parties, or according to the records, the plaintiff extended a loan to the defendant on January 12, 2016 at the rate of KRW 102,682,30,01 in total, among the above loans, at the rate of KRW 100,000,000 per annum 1.5% per annum (15% per annum per annum) on the date of maturity of repayment method, temporary repayment of repayment method, interest rate (interest rate per annum) and interest rate per annum (interest rate per annum 1.5% per annum). As of April 4, 2017, the defendant is obligated to pay to the plaintiff for delay damages calculated on April 15, 2017.
Therefore, the plaintiff's claim shall be accepted on the grounds of its reasoning, and it is so decided as per Disposition.