(영문) 대전지방법원 2020.10.15 2020가단118503
구상금
Text

The Plaintiff

A. Defendant A Co., Ltd.: 763,068,427 won and 760,369,861 won among them shall be from April 2, 2020 to April 2, 2020.

Reasons

1. Determination as to the cause of claim

A. Facts of recognition 1) The Plaintiff is Defendant A Co., Ltd. (hereinafter “A”).

A) Around January 2019, the Plaintiff and Defendant A entered into the following credit guarantee agreement with each other. Around January 17, 2020, the term of the first credit guarantee agreement was changed to January 17, 2020. The Plaintiff and Defendant A paid the Plaintiff the amount of the guaranteed obligation, the amount of the guaranteed obligation discharged to the Plaintiff, the amount of damages for delay determined by the Plaintiff from the date of repayment of the guaranteed obligation to the date of repayment of the guaranteed obligation, the amount of damages for delay, the penalty for subrogation, the penalty for delay, the amount of penalty for negligence, etc., determined by the Plaintiff, from the date of repayment of the guaranteed obligation, to the date of repayment of the guaranteed obligation.

The networkF has jointly and severally guaranteed the defendant A's above obligations.

3) In accordance with the above credit guarantee agreement, the Plaintiff is a stock company G (hereinafter “G”).

The Plaintiff issued each credit guarantee form as follows. On January 10, 2019, the Plaintiff notified G that the term of the first agreement was changed to January 17, 2020. The Defendant A received a loan from each of the above credit guarantee forms as follows, on September 18, 2019, at H510,000,000 Won of the guaranteed principal of the guaranteed number on the date of issuance of the first credit guarantee agreement, on January 19, 2019:

On December 5, 2019, G notified the Plaintiff on December 5, 2019, that a credit guarantee accident under arrears with interest of the Defendant A occurred in relation to each of the above loans of KRW 600,00,000 for general loans of KRW 600,000,000 for general loans of KRW 2.330,000 for 20,000 for 204.24, 2018. The Plaintiff notified the Plaintiff on April 2, 2020 that a credit guarantee accident under arrears with interest of the above loans of KRW 930,00,000 for 330,000 for 20,000 for 20,000 for 20,000 for 20,000 for 20.