Text
1. The Defendants jointly and severally pay the following amount to the Plaintiff:
(a) 16,158,700 won;
B. The above A.
subsection (b).
Reasons
The relevant Plaintiff between the parties based on the facts is the owner of the building indicated on the ground (hereinafter referred to as the “instant building”) and the building C on the ground (hereinafter referred to as the “C building”) of the Daejeon Seo-gu B’s land (hereinafter referred to as the “instant land”).
Defendant Liber General Construction Co., Ltd. (hereinafter “Defendant Liber General Construction”) is the executor of the instant construction work (hereinafter “instant construction work”) that newly constructs the 4th underground and the E Urban Residential Housing of the 15th floor above the ground surface (hereinafter “instant apartment”) on the land adjacent to the instant land and building, Daejeon Seo-gu, Daejeon. Defendant Liber Construction Industry Co., Ltd. (hereinafter “Defendant Liber Construction Industry”) is the contractor of the instant construction work.
The instant construction project, including the content of the instant construction project, commenced around March 2012 and completed around October 2013. During the construction project, the construction project was conducted from April 2012 to December 2, 2012.
The Soil G-PLE construction is one of the general opening construction methods in H-PLE earth and so it is a construction method that sets up earth walls after inserting and digging earth and sand into Auger (H-PLE) by inserting and digging earth and sanding so as to create earth and sand walls up to the prescribed depth.
In general, this is the most economical and easy construction management as a public law that is used in many ways, and the small equipment is so small that it can be treated relatively easily.
However, when installing earth and sand boards, there is a problem of earth and sand room and there is a strong strength of earth and sand, so it is likely to cause damage to neighboring buildings, and it is urgently required to measure and manage the earth and sand, and there is a possibility that the earth and sand erosion may occur due to the completion of excavation.
In addition, the ground of CIP method is excavated by Auger, aggregate such as inserting steel divers after inserting steel divers, and injecting Morar.