(영문) 수원지방법원 여주지원 2018.05.17 2018가단864
건물인도
Text

1. The defendant shall be the plaintiff.

(a) deliver the buildings listed in the separate sheet;

B. From January 31, 2018, KRW 600,00 and the above A.

Reasons

1. Indication of claim;

A. On October 17, 2017, the Plaintiff and the Defendant concluded a lease agreement with the Defendant setting the lease term as KRW 300,000 per month on the attached list owned by the Plaintiff (hereinafter “instant building”) by the month in which monthly rent is deposited. The Plaintiff and the Defendant concluded a lease agreement with the Defendant setting the rent as KRW 300,000 per month (the 30th day of each month on the payment date).

B. However, the Defendant did not pay rent after December 30, 2017, and the rent was overdue for two months. The Plaintiff terminated the said lease contract with the Defendant.

C. Therefore, the Defendant is obligated to deliver the instant building to the Plaintiff, and pay damages equivalent to the rent of KRW 600,000,000 per month from January 31, 2018 to the completion date of delivery of the said building.

2. Article 208 (3) 1 of the Civil Procedure Act of the applicable provisions of Acts;