(영문) 서울중앙지방법원 2016.10.06 2014가합42115
용역대금
Text

1. The Defendant (Counterclaim Plaintiff) paid KRW 142,080,000 to the Plaintiff (Counterclaim Defendant) and its related amount from August 28, 2014 to October 6, 2016.

Reasons

1. Facts of recognition;

A. The Plaintiff is a company with the objective of 3D multi-level film-related service business, computer traffic service business, etc., and the Defendant is a company with the objective of producing and planning film, drama, and animation.

B. On March 3, 2014, the Defendant entered into the instant service contract, after receiving a contract from Russia Company for the production of animation (hereinafter “instant animation”) and then, on December 17, 2013, the Plaintiff had already received the first data from the Defendant to receive animation data and conducted animation data assessment and work.

Of them, the Plaintiff entered into a service contract with the Plaintiff on certain quantities (hereinafter “instant service contract”), and the main contents thereof are as follows.

Defendant : Plaintiff A: A enters into force from the date of conclusion of the contract, and the provision of all services required for this animation is completed, as specified in Article 4 of this Agreement, and the work-related data have been obtained in writing after delivery to Party A.

(1) The title of animation subject to this contract is as follows:

The title of animation: A (Gai : Russian theater 3D animation) (2) The total professional length is 8.96 minutes.

(3) Except as otherwise designated in the work manual, the work to be performed is very large as follows:

Stage A: Animation (Bocking, Pse, Final)/Stero/Dynamics (4) will comply thoroughly with the work manual of the contract and implement work based on the work data and data provided by A as indicated in the work manual.

(5) Both Party A and B intend to use Alibrain Esentist Program (Alibrain) and Cerebro Program (Cerebro) in relation to the transfer and acquisition of goods procured and subordinate goods, and the transfer and acquisition of materials and data provided by Party A.

arrow