(영문) 수원지방법원 2011.05.18 2010구합680
손실보상금
Text

1. The Defendant: (a) KRW 216,558,800 to the Plaintiff; (b) 5% per annum from November 4, 2009 to May 18, 201; and (c).

Reasons

1. Details of ruling;

(a) Project approval and public announcement - Urban planning facility project (construction works around a housing site development project) - Public announcement at the time of shows, No. 208-71 of November 14, 2008;

(b) Project operator: Defendant;

C. The Central Land Expropriation Committee (hereinafter collectively referred to as “each expropriation ruling of this case”). (1) The land subject to the expropriation ruling of Sep. 10, 2009 (Ga) shall be the land subject to the expropriation ruling of Sep. 10, 200, (1) the amount of compensation of 36-5 forest and field 245 square meters (which was divided into 36-2 forest and field 690 square meters for the instant business), 42,74, 410 won, 36-6, 871 square meters (hereinafter referred to as “the remaining land of this case”) of 36-3,000,000,000,0000 7,000,0000,000,000 36-1,000,000,000,000,000,000 37,000,000,000).

(C) The date of commencement of expropriation: The Korea Appraisal Board Co., Ltd., the Korea Appraisal Board Co., Ltd., the two appraisal corporations (2) the business branch offices of the two appraisal corporations, which were located on December 17, 2009. The land subject to the adjudication of expropriation (A) and the amount of compensation shall be interested at the time of the commencement of expropriation.