(영문) 광주지방법원 2019.01.11 2018가단16565
공사대금
Text

1. The defendant shall pay 65,99,000 won to the plaintiff and 15% per annum from July 7, 2018 to the day of complete payment.

Reasons

1. Facts of recognition;

A. On June 14, 2017, the Plaintiff entered into a subcontract with the Defendant for the construction cost of KRW 374,000,000 (including additional tax) with respect to the steel framed and Chang Lake Project, among the Jeju-si Model Project, located D, and entered into a contract for the modification of the contract on August 14, 2017 with the construction cost of KRW 448,459,00 (including additional tax).

B. Although the Plaintiff performed a subcontracted project from the Defendant and completed the subcontracted project on October 31, 2017, the Plaintiff did not receive KRW 65,99,000 out of the construction cost of KRW 448,459,00 from the Defendant.

[Ground of recognition] Facts without dispute, Gap evidence Nos. 1 through 5, purport of whole pleadings

2. According to the above facts of recognition, the Defendant is obligated to pay the Plaintiff the construction cost of KRW 65,99,000 and the damages for delay calculated by the ratio of 15% per annum from July 7, 2018 to the date of full payment, which is the day following the delivery date of the original copy of the instant payment order, to the day of full payment.

3. Thus, we conclude that the plaintiff's claim of this case is reasonable and acceptable.