Text
1. The Plaintiff:
A. Defendant 2,363,541,970 won and KRW 1,171,649,387 out of the said money.
Reasons
1. Determination as to the cause of claim
A. There is no dispute between the Plaintiff and the Defendants as to the facts stated in the separate sheet.
B. Therefore, with respect to the loan of KRW 1.5 billion on April 13, 2006, the Plaintiff, as the principal obligor, is obligated to pay damages for delay calculated by adding the agreed interest rate of KRW 20% from March 31, 2015 to the date of full payment, which is the agreed interest rate of KRW 1,171,649,387, which is the remainder of the loan principal among the above money, to the Plaintiff. Defendant A, as the joint surety for the above obligation, is jointly and severally liable with Defendant B&C, which is the limit of collateral guarantee, within the limit of KRW 1,950,00,000, which is the limit of collateral guarantee out of the above loan amount.
② With respect to loans of KRW 100 million on June 21, 2006, the Plaintiff, a primary debtor, is obligated to pay damages for delay calculated at the rate of 20% per annum, which is the annual interest rate of 193,00,000,000,000 of the principal of the loan, to the Plaintiff as to the total amount of the principal and interest of KRW 193,009,529, and the above money, from March 31, 2015 to the date of full payment. Defendant A and Red Construction Co., Ltd, a joint surety for the above obligation, are jointly and severally and severally liable to pay KRW 130,00,00,00 each of the above principal and interest of KRW 130,00,00,00,000, and KRW 130,000,000,000, which is a joint and several surety for the above obligation, and KRW 130,000,00,033333).
2. Conclusion, the Plaintiff’s claim against the Defendants is with merit, and it is so ordered as per Disposition.