(영문) 대구지방법원 2020.11.26 2020나303616
부당이득금
Text

The part against the defendant in the judgment of the first instance shall be revoked.

The plaintiff's claim against the defendant is dismissed.

The plaintiff.

Reasons

The scope of the judgment of the court of first instance, which accepted the plaintiff's claim against the defendant and C, dismissed the claim against D, and only the defendant appealed against it, the part of the judgment of the court of first instance as to the claim against C and D is separate and finalized, and the scope of the judgment of this court is limited to the claim against the plaintiff against the defendant.

Basic Facts

The standard construction contract for a private construction project: The construction site for a new construction project for a neighborhood living facility (hereinafter referred to as “instant construction project”): The date of commencement on May 10, 2018: The date of completion: the amount of the construction project for the three-month period after the commencement: the amount of the construction project for the three-month period: the amount of the construction project for the three-month period: KRW 330,000 (10%) the amount of the deposit for the three-month period: the amount of the deposit for the three-month period (33,00,000 won): the amount of the deposit for the three-month period (33,00,000 won): the amount of the deposit for the three-month period: 20% payment for the daily amount: 30% at the completion of the aggregate construction - the amount of the deposit for the one-day period at the completion of the external work - the amount of ten percent

9.12. (Omission) A contractor and a contractor shall enter into a contract by agreement and undertake to perform their contractual obligations in good faith and sincerity, and shall prepare two copies of the contract document as evidence of this contract and keep one copy of each contract document.

Documents to be attached:

1. One copy of the general terms of a contract for private construction works;

2. Design drawings and calculation sheets, the address of the contractor for the work, and the account for the payment of the G C work price among the plaintiffs with the name of the plaintiff in the Daegu Si of Si of Si of Si of Si of Si of Si of Si of Si of Si of Si of Si of Si of Si of Si of Si

A. On May 8, 2018, the Plaintiff entered into a contract (hereinafter “instant construction contract”) with C to newly construct two-story houses on the ground of the old Si-U.S.-si E (hereinafter “instant construction contract”).

B. On May 9, 2018, the Plaintiff paid the down payment of KRW 30 million to C as a check, and then, until August 9, 2018, remitted the construction payment to the bank account of the wife C, and paid KRW 232 million in total.

C. The Plaintiff’s content that included C’s claim for damages due to delay of construction work (as of September 27, 2018) and this.