1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Basic facts
A. The Plaintiff (hereinafter “Plaintiff”) was a company established on July 14, 2009 for the purpose of human resource contract, worker dispatch, and service brokerage business, etc. on the part of July 14, 2009, and the Defendant was a company established on May 19, 1989 for the purpose of automobile, electronic parts manufacturing and sales business, etc.
B. From August 1, 2009 to April 30, 2014, the Plaintiff manufactured and supplied automobile parts (saging and painting parts) to the Defendant, but concluded a contract with the Defendant to lease the buildings, facilities, etc. necessary for manufacturing the said parts (hereinafter “instant contract”).
When concluding the aforementioned contract with the Defendant, the Plaintiff dispatched the employees employed by the Plaintiff to the Defendant to engage in the business of assembling and assembling the automobile parts produced by the Defendant.
The main contents of the instant contract are as follows.
The purpose of this Agreement is to provide for all matters concerning the contract for the supply of private and painting parts and to ensure that both the defendant and the plaintiff comply with the contract in good faith.
Article 5 (Unit Price of Contract)
1. The unit price of the contract shall correspond to the unit price agreement agreed between the defendant and the plaintiff, and shall be added to or deleted from the unit price agreement at the time of addition or deletion of ITM and the unit price agreement shall be repealed;
2. The monthly contract cost for the method of calculating the price shall be calculated from the first day of each month to the last day of each month by the amount for the performance and completion of the work provided by the plaintiff.
3. Adjustment of the contract amount shall, in principle, be made once a year, but the contract amount may be adjusted after consultation between the defendant and the plaintiff, even during the contract period, where any change in the conditions of management, change in the contents of the contract obligation, or any other reason necessary for
4. Claims for and payments of the contract cost.