logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 광주지방법원 2019.01.10 2017가단526201
공사대금
Text

1. The Plaintiff (Counterclaim Defendant) paid KRW 28,710,000 to the Defendant (Counterclaim Plaintiff) and the amount from March 21, 2018 to January 10, 2019.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. Basic facts

A. On March 31, 2016, D Co., Ltd. entered into a contract for construction works with regard to the amount of KRW 1,783,639,00 with respect to G facilities (hereinafter “instant construction”) within the Navy EthicalF of the Maritime Affairs Council of the Armed Forces and the Jeonnam-gun, Jeonnam-gun, for the construction of the G facilities (hereinafter “instant construction”) in the amount of KRW 1,783,639,000, the date of commencement, April 8, 2016; the date of completion; November 30, 2016; and 0.1% of the liquidated damages rate; and the Defendant was awarded a subcontract from D Co., Ltd. for the instant construction works (hereinafter “instant reinforced concrete construction”).

B. On August 2016, the Plaintiff and the Defendant concluded a contract with respect to the instant reinforced concrete construction (hereinafter “instant contract”) with the following terms (hereinafter “instant contract”).

Direct Execution Agreement

1. Name of the original project: G facility construction (3019);

2. Names of direct construction works: Construction works of reinforced concrete;

4. Construction period: The agreed amount on November 30, 2016, the completion date of August 30, 2016, which was the 5th day of November 30, 2016: Japanese Won (e.g. 550,000,000), and 10. Penalty rate for delay: Article 2 (Construction, etc.) of the terms and conditions of the direct performance agreement under the same application as the original contract: (i) the Plaintiff shall perform the construction works in accordance with the terms and conditions of this agreement and design drawings (construction specifications, design drawings).

(2) The plaintiff shall prepare a schedule for construction works and obtain approval therefor from the defendant without delay.

C. According to the instant contract, the Plaintiff implemented the instant reinforced concrete construction; around December 31, 2016, the Plaintiff completed the assembly of the 2nd floor sloping roof and the steel processing assembly of the sloping roof; on January 18, 2017, the preparation work for the sloping concrete sloping sloping sloping sloping sloping sloping sloping sloping sloping sloping slopings on January 19, 2017; the work for the sloping sloping sloping slopings from January 20 to February 25, 2017; and the work for the production of concrete from January 20 to February 9, 2017; the work for the sloping sloping sloping sloping sloping on February 17, 2017; and the work for the removal of the instant temporary materials from the construction site on February 25, 2017.

The defendant shall make the plaintiff on March 3, 2017.

arrow