Text
The defendant shall pay 211,627,198 won to the plaintiff and 12% per annum from August 23, 2020 to the day of complete payment.
Reasons
1. Indication of claims: The sum of the amount payable for the goods, such as hambber, which the Plaintiff supplied to the Defendant from October 2018 to December 31, 2018 (specific details are as shown in the attached Form), KRW 211,627,198, which the Plaintiff supplies to the Defendant (Article 208(3)3 of the Civil Procedure Act).
3. The Plaintiff partially dismissed part of the payment order of this case claimed damages for delay calculated at the rate of 15% per annum from the day after the original copy of the payment order of this case to the day of full payment. However, since the provision on statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings was amended, 12% per annum is applied to damages for delay from June 1, 2019, and thus, the part seeking damages for delay