1. The Defendant’s KRW 141,450,00 for the Plaintiff and 5% per annum from November 15, 2015 to November 17, 2016.
Reasons
1. Facts of recognition;
A. Pungsung Housing Co., Ltd. (hereinafter “Pungsung Housing”) and C Co., Ltd. (hereinafter “C”) decided to jointly carry out apartment construction projects (hereinafter “instant project”) within the Dilju City of Pakistan, and purchased the project site.
B. On March 24, 2004, the Defendant concluded a sales contract with respect to the area of 3,042 square meters and F-road 76 square meters (hereinafter “each of the instant lands”) prior to E in the period of Pakistan owned by the Defendant, as follows:
(hereinafter “instant sales contract”). The purchaser column of the instant sales contract signed and sealed a scenic house, and C, at the bottom of the contract, signed and sealed as a joint executor.
A real estate sales contract (hereinafter referred to as "A") and a joint executor C (hereinafter referred to as "B") shall be called a buyer's scenic house and a joint executor's house (hereinafter referred to as "B") to enter into a sales contract for each land of this case as follows, and implement the contents of the contract on the basis of mutual trust and good faith.
Article 1(Purpose of Contract) In order to purchase each of the instant land owned by “A” and to build urban development projects and multi-family housing in the entire project site within the additional cadastral map (hereinafter referred to as “project site”), the “B” and “B” enter into a sales contract through mutual consultation.
Therefore, the contents of each section of this contract are for the purpose of constructing multi-family housing and neighborhood living facilities.
Article 2 (Sales Price and Payment Method) The purchase price of each land of this case is KRW 1,414,50,000, and the down payment is KRW 141,450,000,000 within 30 days from the date of completion of purchase of the land subject to the project, and the remainder KRW 1,273,050,00 shall be paid within 30 days from the date of completion of purchase of the land subject to
Article 3 (Cancellation of Contracts)
1. This contract is concluded on the premise of a multi-family housing project of “B”, and if it falls under either of the following, only the notification of “B” may cancel this contract:
1 Change of urban planning;