(영문) 서울서부지방법원 2019.04.05 2018나40277
소유권이전등기
Text

1. The plaintiff's appeal is dismissed.

2. The costs of appeal shall be borne by the Plaintiff.

The purport of the claim and appeal is the purport of the appeal.

Reasons

1. The reasoning of the judgment of the court of first instance cited in the judgment of the court of first instance is as follows: (a) the term “one parcel of land” in the first instance on the ground of the judgment of the court of first instance is modified to “one parcel of land”; and (b) the Plaintiff’s assertion added or emphasized by this court is identical to the ground of the judgment of the court of first instance, except for the addition of the Plaintiff’s assertion added or emphasized by this court

2. Additional determination

A. On August 9, 2012, the Plaintiff’s assertion that the route approval by the Mapo-gu Seoul Metropolitan Government public announcement G is indicated only by the starting point, terminal point, extension, etc., and the location, area, etc. of a road zone is not indicated, and Article 25 of the Road Act (Determination of a road zone) of the Road Act (Article 25 of the Road Act) (1) of the Road Act is publicly notified as to the designation, alteration, or abolition of the road route, the road management authority shall immediately

(2) Notwithstanding paragraph (1), a road management authority in charge of an upper-tier road (hereinafter referred to as " upper-tier road management authority") may determine, alter, or abolish a road zone for a intersection or intersection at a lower-tier road (referring to a road higher than the relevant road according to the order of priority specified in Article 10; hereinafter the same shall apply) connected or connected to the relevant upper-tier road.

In such cases, the higher road management authority shall obtain prior consent from the road management authority of a lower-tier road (hereinafter referred to as " lower-tier road management authority").

(3) Where a road management authority determines, alters, or closes a road zone pursuant to paragraph (1) or (2), it shall publicly notify, as prescribed by Ordinance of the Ministry of Land, Infrastructure and Transport, specifying the reasons, location, and size of the road zone and other matters prescribed by Presidential Decree, and make drawings available

Article 24 of the Enforcement Decree of the Road Act (Determination, etc. of Road Zones) (1) When a road management authority determines or alters a road zone pursuant to Article 25 (1) of the Act, it shall implement road works that include the following matters: