logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울남부지방법원 2015.07.02 2014가합109618
손해배상(기)
Text

1. The Defendants jointly share KRW 15,839,658 against the Plaintiffs and each of them, Defendant C Co., Ltd. on October 8, 2014.

Reasons

Basic Facts

On January 16, 2012, the Plaintiffs entered into a contract for the Plaintiffs to enter into a contract with the construction period fixed from February 15, 2012 to July 15, 2013, the construction period of construction of the construction of the land officetel E (hereinafter “instant building”) for the construction company for the construction of the land (hereinafter “instant construction”) of Jung-gu Seoul Special Metropolitan Construction Co., Ltd. (hereinafter “Large General Construction”) (hereinafter “instant construction”) (hereinafter “instant construction”). The Plaintiffs agreed to enter into a contract for the construction of the construction period from February 15, 2012 to July 15, 2013, the construction amount of KRW 11,900,000,000 for construction

On April 25, 2012, the F and G (hereinafter collectively referred to as “H”) entered into a contract with Nonparty F and G ( collectively referred to as “H”) under which the instant electrical construction (hereinafter referred to as “instant electrical construction”) from the General Construction to the construction cost is KRW 970,00,000 (excluding value-added tax) and the construction period from April 25, 2012 to July 15, 2013 (hereinafter referred to as “instant subcontract”).

H had the Defendants perform the instant electrical construction.

On the other hand, on March 1, 2012, H had not received KRW 300 million out of the construction cost, even though he had completed the construction by subcontracting the electrical construction (hereinafter “I electrical construction”) among the new construction works of Gangdong-gu Seoul Metropolitan Government I building with the construction cost of KRW 485,00,000 (excluding value-added tax).

The Plaintiffs did not prepare and give the direct payment agreement with H, and H and the Defendants demanded the Plaintiffs to pay the remainder of the construction cost under the instant subcontract and pay the amount of the I Electric Construction outstanding KRW 300,000,000,000.

On February 4, 2014, Defendant D removed parts installed at the construction site of this case in order to interfere with the inspection for the completion of the building of this case. On February 6, 2014, the Plaintiffs drafted a direct payment agreement and written confirmation.

arrow