(영문) 서울행정법원 2018.03.29 2017구단74866
손실보상금
Text

1. The Defendant’s KRW 96,741,00 for the Plaintiff and KRW 5% per annum from May 3, 2017 to March 29, 2018.

Reasons

1. Details of ruling;

(a) Business approval and public announcement - Business name: Public housing project (Seoul High River - Business operator: Defendant - Business approval: Designation of the Bogeumjari Housing District in Seoul High River 201-753 announced by the Ministry of Land, Transport and Maritime Affairs on December 8, 201 and public announcement of topographic drawings, etc.;

B. The adjudication of expropriation by the Central Land Tribunal on March 9, 2017 - The expropriation object owned by the Plaintiff: ① 36-2 large scale 194 square meters (hereinafter “instant land”); ② 36-4 large scale 308 square meters (hereinafter “instant land”); ③ the above 36-5 large scale 30 square meters (hereinafter “instant land”); and ③ the instant land is 36-5 large scale 60 square meters (hereinafter “instant land”) and other obstacles, such as the building owned by the Plaintiff, were also expropriated, but the Plaintiff did not seek an increase in compensation for obstacles; and accordingly, the court’s appraisal on the obstacles was not conducted.

- From May 2, 2017: 1,970,595,00 won in total of each of the instant lands (i) the instant land of KRW 1,170,80,800,400 in the instant case (ii) the instant land of KRW 1,170,800,400 in the instant land; (iii) the appraisal corporation and the appraisal corporation and the appraisal corporation and the appraisal corporation and the appraisal corporation and the appraisal corporation and the appraisal corporation and the one-day appraisal corporation: The comparison standard land - all of the above two appraisal corporations [commercial use: development-restricted area, development-restricted area, natural green area, and road traffic: The assessment of the land of KRW 431-4,198 square meters in the Gangdong-gu Seoul Metropolitan Government (commercial use: development-restricted area, natural green area, and road traffic: the assessment of the appraised value of neighboring land within the limit of 1/3 of the appraised value of neighboring land because the present status of use of the instant land was a road).

C. Determination by the Central Land Tribunal on September 21, 2017 - Compensation for losses: Total amount of KRW 2,050,644,200 for each of the instant lands (i.e., the instant land KRW 1,182,042,400 for the instant land ② The instant land KRW 1,182,042,40 for the instant land ③ An appraisal corporation: A certified public appraisal corporation and the central appraisal corporation for the resolution of disputes.