(영문) 대구고등법원 2015.02.06 2014누367
손실보상금증액등
Text

1. The defendant's appeal is dismissed.

2. The costs of appeal shall be borne by the Defendant.

3. Attached Form 1 of the Judgment of the court of first instance.

Reasons

1. In the first instance court, the Plaintiff filed a claim for KRW 52,148,250 for compensation for losses on the ground axiss (hereinafter “the instant land”) of KRW 1,871,50 square meters for permanent residence, and KRW 52,148,250 for compensation for losses on the land axiss (hereinafter “the instant land”) of KRW 780 square meters for permanent residence, and the first instance court rejected the remainder of the claims under the above paragraph (1) and (2).

As to this, the defendant only appealed with regard to the part of the above claim (2) as stated in the purport of the above appeal, the scope of the court's trial is limited to the above claim (2).

2. Details of ruling;

A. Approval and Public Notice of Project - Dam Construction Project (hereinafter “instant Multipurpose Dam Construction Project”) - Defendant: AD announced by the Ministry of Land, Transport and Maritime Affairs on June 29, 2009, AE announced by the Ministry of Land, Transport and Maritime Affairs on February 10, 2010

(b) The Central Land Tribunal’s ruling of expropriation on September 2, 201 (hereinafter “adjudication of expropriation”): 1/2 shares in the instant land owned by the Plaintiff and FP large 241 square meters for permanent residence; - The instant obstacles - Compensation for losses: Compensation for losses of each of the instant land; 265,212,00 won for losses of the instant obstacles; and 265,212,00 won for losses of the instant obstacles - the date of commencement of expropriation: The Korea Appraisal Board, the Korea Appraisal Board, and the Korea Appraisal Board (hereinafter “appraisal of expropriation”): (hereinafter “appraisal of expropriation”):

C. The Central Land Tribunal rendered an objection on February 17, 2012 (hereinafter “Adjudication”): The content of the adjudication: The application for the increase of compensation for losses for each of the above land is dismissed, and the compensation for losses for the obstacles in this case is increased to KRW 268,304,300; the State appraisal corporation and the stock company.