(영문) 창원지방법원통영지원 2019.01.17 2018가합10056
사용료
Text

1. The Defendant shall pay to the Plaintiff KRW 37,090,210 and the interest rate of KRW 15% per annum from December 12, 2017 to the date of full payment.

Reasons

1. Basic facts

A. The Plaintiff is a corporation established under the Korea Electric Power Corporation Act to operate the development, development, transmission, distribution, and related businesses of electric resources. The Defendant is a corporation that runs the maritime transport business, the fishery business, the deep sea and the coastal fishing business.

B. On December 24, 2013, the Defendant’s local fishery product hub distribution center operator and subsidies granted to the Defendant. On December 24, 2013, the regional distribution center for fishery products (FPC) implemented by the Ministry of Oceans and Fisheries (FPC) and distribution center for fishery products (FPC (FPC) and the center for producing and selling fishery products to consumers through pre-processing and processing, such as clustering, washing, screening, packing, etc. in mountainous districts; hereinafter the “regional distribution center for fishery products operated by the Defendant”.

[2] The head of B/Gun notifies the Defendant on December 26, 2013 that the head of B/Gun was selected as the instant distribution center operator on the following grounds: (a) the project cost of the instant distribution center project, the total project cost of the business operator and the total project cost of the National Treasury-Si/Gun-in-Si/Gun-in-Si/Gun-in-Si/Gun-in-Si/Gun-con-Si/Gun-in-Si/Gun-in-Si/Gun-in-Si/Gun-in-Si/Gun-in-Si/Gun-in-Si/Gun-in-Si/Gun-in-Si/Gun-in

3) On April 14, 2015, the Defendant filed an application with B head of the Gun to grant subsidies of KRW 2.5 billion, excluding KRW 2,684,905,00 of the total project cost of the distribution center of this case, from among the total project cost of KRW 5,184,905,000, to the Defendant. C. The Defendant contracted the construction of the distribution center of this case and the contract for electric use between the Plaintiff and the Defendant, etc. for the execution of the electric construction of the distribution center of this case. (1) The Defendant contracted the construction of the electric facilities (hereinafter “instant electrical construction”) among the construction works of the distribution center of this case to C (hereinafter “C”) and delegated the Plaintiff with the application for electric use.

2) On June 4, 2015, C is the Plaintiff’s senior branch office on behalf of the Defendant (hereinafter “senior branch office”).

this subsection.