(영문) 창원지방법원 2020.08.13 2019구합53189
건축허가 거부처분 취소
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Details of disposition;

A. On June 12, 2019, the Plaintiff filed an application with the Defendant for permission to construct graveyard-related facilities (animal crematory facilities, animal-only charnel facilities, building area 19.59 square meters, total floor area 234.23 square meters) on the ground of Jinju-si Bri (hereinafter “instant application site”) and for permission to engage in development activities deemed a building permit, and 97 square meters out of the instant application site and adjacent D road 535 square meters (hereinafter “instant road site”), the instant application site for permission to divert farmland, the instant application site for permission to divert farmland, reports on installation of private sewage treatment facilities, and permission to occupy and use the instant road site.

(hereinafter referred to as “instant application”) . Permission to use public property on the ground of rejection of the application for permission to construct title (application) - Permission to use the relevant lot number (D) - Construction proposal for the village park creation (E, June 19, 2019) shall be received and reviewed, and consultation is not possible at the present time pursuant to Article 30 of the State Property Act - Building site and road - Building site at least two meters shall be adjacent to roads (excluding roads used exclusively for vehicle traffic) pursuant to Article 44 of the Building Act; however, the relevant building site does not adjoin roads, and it does not adjoin the roads, and it does not adjoin the roads, and construction of graveyard-related facilities (animals) of the third floor size of the building at the Gu hill area of the conservation and control area where the building is applied for, and construction of graveyard-related facilities (animals) of the third floor size of the building is not formed around the surrounding forest landscape; construction of the building at the outermost construction line - installation of the building at the site requiring serious improvement of the boundary of the local highway or adjacent road (road).

arrow