(영문) 서울고등법원 2015.03.24 2014누7550
손실보상금
Text

1. The portion of a claim for compensation for losses due to a decrease in the price of remaining land and remaining buildings in the judgment of the first instance shall be revoked;

Reasons

1. The scope of the trial in this case is to seek the plaintiff's increase in compensation for expropriation of the land expropriated due to the defendant's urban planning facility project (2nd construction work in the vicinity of a housing site development project) and the payment of compensation for expropriation of the remaining land and the remaining building due to a price decrease. The first instance dismissed the claim for increase in compensation for expropriation of the expropriated land and the claim for compensation for expropriation of the remaining land and the remaining building, respectively, and accepted the claim for compensation for compensation due to a price decrease in the remaining land and the remaining building (216,58,800 won: 216,58,800 won). With respect to the claim for compensation for expropriation of the expropriated land and the remaining land and the claim for compensation for expropriation due to price decrease in the remaining land (2nd construction work in the vicinity of a housing site development project in the urban development project in the urban development zone), the defendant filed each appeal on the remaining land and the remaining land (the part against the defendant's loss) and the defendant's appeal on the compensation for expropriation of the expropriated land and the remaining land.

In this regard, only the defendant appealed against the defendant during the judgment before remand, and the Supreme Court reversed the remaining land and the remaining building's price decrease and remanded.

Therefore, the portion of each of the claims in this case before remanding is determined and excluded from the scope of the judgment of this court, as the remaining claims except for the portion of compensation for losses due to a decrease in the price of remaining land and remaining buildings, the scope of the judgment of this court is limited to the portion of the above reversal and