(영문) 수원지방법원 2016.12.15 2015구합66623
손실보상금
Text

1. The Defendant: (a) KRW 101,613,500 to Plaintiff A; (b) KRW 5,460,00 to Plaintiff B; and (c) from February 7, 2015 to December 2, 2016 to each of them.

Reasons

1. Circumstances and results of appraisal of the ruling;

(a) Project name: The public notice of the industrial complex development project (C general industrial complex development project) 2: The defendant; D public notice of Gyeonggi-do on December 5, 2013; and E public notice of Gyeonggi-do on May 29, 2014;

B. The subject of expropriation by the local Land Tribunal of Gyeonggi-do on December 23, 2014 - Plaintiff A: (a) 【Land subject to Expropriation” as indicated in the “B’s list of compensation details” - Plaintiff B: The land indicated in the “land subject to expropriation” as indicated in the “land subject to expropriation” as indicated in the “B” list of compensation details” (hereinafter collectively referred to as “each land owned by the Plaintiffs”), and the parcel number shall be indicated only when the individual land is named.

(2) 2) - Plaintiff A: 3,855,865,500 won in total of the land (for each land, the compensation amount shall be the same as the corresponding amount stated in the “adjudication on Expropriation”) and 15,000,000 won in total of obstacles - Plaintiff B: The starting date of expropriation: 244,920,000 won in land: June 25, 2015; the Central Land Expropriation Committee’s ruling on June 25, 2015 - The compensation amount for each land of this case shall be changed to the corresponding amount indicated in the “Adjudication” in the following table; and the objection against Plaintiff A’s obstacles shall be dismissed (hereinafter the result of appraisal in the above Adjudication is referred to as “appraisal”).

D. The result of the court’s entrustment of appraisal to the appraiser G (hereinafter “court appraiser G”) and the result of the court’s entrustment of appraisal is “court appraisal”

- The appraised amount: The appraised amount for each land of this case is 15,58,00 won in total, as stated in the “court appraisal amount” column in the statement of compensation details, and the appraised amount for obstacles is 15,58,000 won in total.

The court appraiser calculated the H land appraisal amount by dividing the cases where the light water reduction is considered according to the plaintiffs' request for appraisal commission and the cases where the exclusion is made.

arrow