Text
1. The Defendants shall jointly and severally pay to the Plaintiff KRW 1,165,400,00 and the interest rate thereon from February 21, 2013 to the date of full payment.
Reasons
1. Facts of recognition;
A. 1) The Plaintiff is a company that produces and sells broadcast programs. The Plaintiff is a company that produces and sells broadcast programs. 2) Defendant B is a drone, and Defendant C is a broadcasting planning company.
B. On February 16, 2010, F entered into a drama writing contract between G, H, E, and F to write the drama dramatic diala of G, H, E, “I” and “J” into between G, H, and E, and F to pay KRW 700 million to G, H, and E in the form of a extreme script (hereinafter “instant writing contract”).
C. On July 28, 201, the Plaintiff acquired the right under the instant written contract (i.e., acquisition of the right under the instant written contract) by transfer from F in the amount of KRW 450 million upon the recommendation of Defendant B and C (hereinafter “instant transfer contract”).
(2) On July 28, 201, the Plaintiff paid F a total of KRW 450 million on October 28, 201, and KRW 450 million on October 28, 201.
3) On July 20, 201, the Plaintiff entered into a license agreement with G, H, E, and Defendant B to write the drama drama in the so called “I”, “J,” and Defendant C, at the same time as the planning agent at the time the said agreement was entered into. D. The Plaintiff’s separate license agreement was entered into on November 11, 201, with the recommendation of Defendant C, to write the drama in the so called “L” amounting to KRW 350,000,000,000,000 won.
The above drone writing contract states that the defendant C bears the responsibility of the planning authority for the progress such as the dramatic drama and the formation of the public wave.
2) On November 11, 201, the Plaintiff paid the down payment of KRW 180 million to K. 3) On August 20, 2012, upon Defendant B’s recommendation, the Plaintiff: (a) entered into a drama writing agreement with H and M to write the drama of H and M’s title “N” in the theater fee of KRW 520 million between H and M.