(영문) 대전지방법원 2020.10.15 2019구합102092
입찰참가자격제한처분취소
Text

1. The Defendant’s disposition of restricting participation in bidding against the Plaintiff on March 20, 2019 is revoked.

2. The costs of lawsuit shall be.

Reasons

A. A public announcement was made (hereinafter “instant public announcement of tender”) and subsequent tender was made.

In the public announcement of this case, the contents of this case are as follows.

If a bidder does not enter into a contract due to a failure to enter into a contract due to a specification error or regulation, or fails to enter into a contract, he/she may be punished as an improper businessman pursuant to the relevant Acts and subordinate statutes, and may be subject to disadvantage, such as restricting participation

A participant in this tendering procedure shall be allowed to inspect and be informed of the written public notice, various regulations, work instructions, etc. which form the following tender documentation, and shall inform the bidder that all the responsibilities arising from the failure to be informed of them.

1. Tender outline - Limited Competition - The name of a facility and equipment - The quantity of goods: 1 - The method of tender - The total amount of restrictions (total amount) - the service period: from January 1, 2019 to December 31, 2021 - The estimated price: 154,783,636 won (* Value Added)* Other detailed matters (number of duties, duties, etc.)* shall be based on the document requested by the procuring entity and attached to the electronic bidding notice.

5. The method of determining successful bidders - The method of determining successful bidders - The method of examining successful bidders (the service in the area of facilities and the criteria for evaluating and assessing eligibility examinations: the service in the area of facilities, the estimated price of which is less than 500 million won under the attached Table 2 of Article 5 (1) 2 of the detailed criteria for

C. The Plaintiff participated in the instant bid and was selected as a subject of the qualification examination, and the result of the qualification examination (hereinafter “instant qualification examination”) was determined as follows and was determined as a final successful bidder.

A D

D. Accordingly, on December 28, 2018, the Plaintiff entered into a “B service contract” (hereinafter “instant service contract”) with the Defendant as of December 31, 2019, with the term of 48,366,80 won, and the term of delivery as of December 31, 2019.

The documents included in the instant service contract are included in the appended documents.